What a payment bond does
A payment bond (also called a labor and material bond) guarantees that the subcontractors, laborers, and suppliers on a project are paid. On public projects, those parties cannot file a mechanics lien against public property, so the payment bond is their security. It is almost always issued alongside a performance bond.
When California requires one
On public works the trigger is a dollar figure, not the agency's preference. Under Civ. Code §9550, a direct contractor awarded a public works contract involving more than $25,000 must give a payment bond, approved by the awarding agency, before work begins. The agency has to state that requirement in its call for bids. Contracts with a state entity follow the Public Contract Code instead, with the same result in practice: a bond before the first progress payment.
Private work has no statutory trigger, but it has a statutory incentive. An owner who records the direct contract together with a payment bond of at least 50% of the contract price (Civ. Code §8600) limits mechanics lien enforcement to what the owner still owes the contractor, which is why lenders and developers ask for one. Civ. Code §8602 leaves the owner free to require a full performance and payment bond on top.
How much bond, and from whom
A public works payment bond must be for not less than 100% of the total amount payable under the contract (Civ. Code §9554). It has to be a bond written by an admitted surety, not a deposit in place of one, and it covers unemployment insurance contributions and EDD withholding on the work as well as the subcontractors and suppliers. If the bond is not given and approved, Civ. Code §9552 stops the agency from paying the contractor anything under the contract.
Who can claim, and how long the bond stays exposed
Anyone who provided work under the contract at the direction of the prime, a subcontractor, or the architect can claim, and so can a laborer (Civ. Code §9100). The direct contractor cannot. A claimant is normally expected to have served a preliminary notice; one who did not can still reach the bond by writing to the surety and the contractor within 15 days of a recorded notice of completion, or within 75 days of completion if none was recorded (Civ. Code §9560 on public work, Civ. Code §8612 on private).
The clock matters for your surety record. On public works a claimant may sue on the bond any time after stopping work and no later than 6 months after the stop payment notice window closes (Civ. Code §9558); that window is 30 days after a notice of completion is recorded, or 90 days after completion otherwise (Civ. Code §9356). Recording the notice of completion is therefore the single thing a contractor can do to shorten the exposure. On a private job with a recorded bond the limit is 6 months after completion (Civ. Code §8610). The surety can be sued directly, with or without a stop payment notice, and the prevailing party recovers attorney's fees (Civ. Code §9564), which is why sureties settle valid claims quickly and then look to you under the indemnity agreement.
What it costs
When written with the performance bond, the payment bond is generally covered by the same combined premium, typically 1% to 3% of the contract amount, set by underwriting. We quote the pair together for your specific project; the payment bond cost calculator gives a first estimate on your contract amount. Bid bonds that lead into the pair cost nothing; see bid bonds.
The home improvement version: the blanket bond
Residential contractors meet a payment bond in a different place. BPC §7159.5(a)(3) caps a home improvement down payment at $1,000 or 10% of the contract, whichever is less, and ties every later payment to work actually done. BPC §7159.5(a)(8) exempts a contractor who furnishes a performance and payment bond, a lien and completion bond, or a CSLB-approved equivalent, and lets that contractor accept payment before completion. The CSLB approves a blanket version of the bond for licensees who have been active for at least 2 years. It is underwritten like any contract bond, on financials rather than credit alone, so ask us before you promise a customer a different payment schedule.
