Bid bonds by the numbers
- $150,000
- Federal contract size that requires performance and payment bonds
- Acquisition.gov (FAR 28.102)
Step 1: Read what the bid documents ask for
The instructions to bidders decide everything about your bid bond, so start there. Look for four things:
- The percentage. On state contracts it is at least 10% of the amount bid by statute (PCC §10167). Cities (PCC §20170), counties (PCC §20129(a)) and school districts (PCC §20111(b)) must require bid security but set the amount themselves, almost always 10%.
- The form.Some agencies require their own bid bond form; others accept the surety's standard form or the AIA A310. Federal jobs use the SF 24. A bond on the wrong form can get the bid rejected as nonresponsive.
- The obligee's exact name and the project name or number, as the documents state them.
- How it is delivered. State agencies may accept an electronic bid bond through an approved registry; others want the signed original with the sealed bid.
A bid that arrives without the required security is rejected. On state work, the Code says it "shall not be considered." California bid bond requirements covers the rule in full.
Step 2: Set up your surety program before the bid you care about
The first bid bond is the slow one. Before a surety backs any bid, it underwrites you as if you had already won, because the bid bond promises the owner the performance and payment bonds that follow. Expect to provide:
- Business and personal financial statements, with CPA-prepared statements for larger programs
- A work-in-progress schedule of the jobs you have on hand
- A contractor questionnaire covering your experience, largest completed jobs and key people
- A signed indemnity agreement
The result is a bonding line: a single-job and an aggregate limit the surety will support. The submission packet guide lists what to assemble so the review moves quickly.
Step 3: Request the bond for each bid
With a program in place, each bid bond is a short request. Send us the obligee, project name, bid date, estimated bid amount, required percentage and the agency's bond form if it has one. If the job fits inside your line, the bond is issued and signed by the surety's attorney-in-fact with a power of attorney attached. If it is larger than your line, the underwriter will want to see the job before approving it, which is why a big bid should be flagged early, not the day before.
Step 4: Submit it with the bid, and know what it commits you to
The bid bond goes in with your sealed bid. If you are the low responsible bidder, you must sign the contract at your price and furnish the final bonds. Back out and you forfeit the security: the surety pays the agency's loss, usually the gap to the next bid, up to the bond amount, which on a $500,000 state bid is $50,000. It then recovers that from you under the indemnity agreement. Only bid work you are ready to bond and build.
What it costs
The bid bond is $0 with us. What you pay comes on award: the performance and payment bonds, typically 1% to 3% of the contract for the pair, billed once. On a $500,000 contract that is roughly $5,000 to $15,000. Run your own number through the bid bond calculator, or read why bid bonds are usually free.
New business, thin financials or bad credit
A short track record does not rule you out. The SBA Surety Bond Guarantee program backs bonds on contracts up to $9,000,000 for contractors who do not yet qualify on their own, and our hard-to-place markets write files with credit problems or a prior claim. See how to get bonded with a new business for the path most first-time bidders take. Underwriting always applies, and we never promise approval.